First phase successfully completed at West Hendford

We are pleased to confirm that the first phase of dwellings (3nr flat over garages, 3nr of flats and 6nr 3 bed houses) have been successfully handed over at West Hendford in Yeovil, Somerset.

“I would like to take this opportunity on behalf of Stonewater to thank your team at West Hendford for their continuous hard work during the build period and also there support today on the first handover. Nothing is ever to much to ask of your team and they are a credit to Halsall. I look forward to working with you all on future phases and  projects. The quality of workmanship, site management, QS, and effort cannot be faulted” Joanna Barnard, Stonewater

The project involves the design and construction of 48nr houses, 7nr flat over garages, 1nr block of 6 flats and 1nr block of 3 flats to achieve Building Regulations, together with related external works and drainage.

Client: Stonewater

Value: Circa £6,000,000

Duration & Dates: 84 weeks. Sept ‘15 – May ‘17

Form of Contract: JCT Design & Build 2011

Key Deliverables:

  • Development on a brownfield site providing a second phase for Stonewater
  • Won on competitive tender
  • Timber frame construction incorporating flats over garages, 2 and 3 storeys
  • A compact site layout with a large volume of neighbours
  • A mixture of 1, 2, 3 and 4 bed dwellings fulfilling the urban affordable housing need.

“On behalf of Stonewater we would like to extend our thanks to your team at West Hendford for an excellent scheme. We find David, Andy and all the team exceptionally pro-active and the quality is of a high standard.”

Ian Mooney, Baker Ruff Hannon

Recent Posts

Our Charity Golf Day 2023

Holden Gardens show home

CARGO Work completion photos

Some of our projects

Holden Gardens

Holden Gardens

Holden Gardens

Holden Gardens

CARGO Work

CARGO Work

Brooks Dye Works

Brooks Dye Works