Avon Valley College structural steel frame

The structural steel frame at Avon Valley college was fabricated by Morgans of Usk and delivered to site on the 11th of June. The frame was completed and handed over to us on Thursday the 20th of June. With only a few beams to be located in position once the precast slabs have been installed, these works, starting tomorrow will be completed by Friday the 19th of July.